In the field of drilling, casing pipe, as
a common OCTG
pipe, is an indispensable tool. So what are the methods for installing it
in deepwater wells?
Riser method for casing pipe installation
Riser method is a common method for
deepwater well casing pipe installation, mainly installing casing pipe on the
sea surface. This method can ensure the positioning accuracy of the casing pipe
and can be adjusted during the installation process. Its advantage is that it
can ensure the positioning accuracy of the casing pipe and facilitate
adjustment, but it requires piling construction, which increases the difficulty
and cost of the work.
Riser method installation steps
1. First, piling construction should be
carried out after underwater survey. This ensures that the casing pipe can be
stably placed on the seabed.
2. Then, use a crane or a lifting boat to
place the casing pipe within the steel pipe length and accuracy control range
of the pile driver. The vertical positioning of the casing pipe can be
completed by controlling the length of the steel pipe.
3. When the casing pipe is completely
placed on the seabed, connect the pipe fittings and handle the seals between
the casing pipe and the wellbore.
4. Finally, fill the well to minimize the
buoyancy difference inside and outside the well.
Floating method to install casing pipe
The floating method is a relatively new
method of casing pipe installation, which is suitable for shallow waters. This
method places the casing pipe on a buoy and then transports and installs it by
ship. Its advantage is that it omits the piling construction step compared to
the riser method, reducing the difficulty and cost of the work, but it is not
accurate enough and the position of the casing pipe cannot be adjusted.
Floating method installation steps
1. First place the buoy where the casing
pipe needs to be installed.
2. Then place the casing pipe on the buoy
through the lifting device and ensure that there is no collision between them.
3. When the casing pipe and the buoy are
firmly connected, the ship can be used for backlog connection and the seal
between the casing pipe and the wellbore is handled.
4. Finally, fill the well to reduce the
buoyancy difference inside and outside the well.
Summary
There are two ways to install deepwater
well casing pipe: the riser method and the floating method. Choosing the
appropriate method requires considering the specific situation and needs. At
the same time, during the installation of the casing pipe, some issues need to
be paid attention to, such as the diameter of the wellbore, the length of the casing
pipe, etc. Only by fully mastering the relevant knowledge and strictly
following the operating specifications can the quality and safety of the casing
pipe be guaranteed.